05/19/2024
Spread the love

Reopening of Westbound lanes to begin May 8

 

Contributed photo by Jeffery Hall

Contributed

WILMINGTON – The N.C. Department of Transportation will reopen lanes of the Cape Fear Memorial Bridge this week, completing the preservation project weeks in advance.

“I am proud to be part of the NCDOT and this community,” Division 3 Engineer Chad Kimes said. “The department has worked closely with its partners, which has proven to be key to getting critical messages out, and of course, finishing this project early.”

The westbound lanes of the bridge are scheduled to reopen to traffic on May 8 at 7 p.m. Like the reopening of the eastbound lanes, the process will take several hours to complete as crews will need to change signage and pavement markings and remove barrels.

“I want to thank the public for their patience,” Kimes added. “We know changing your schedules and experiencing additional congestion over the last few months hasn’t been easy. Again, working together has made this project a success all around.”

For several months, an NCDOT contractor has done extensive work to create a smoother, safer ride, while also extending the life of the bridge connecting Brunswick and New Hanover counties. In January, the eastbound lanes closed to replace the grid deck and stringers, the support beams. The contractor finished the work ahead of the Azalea Festival. After the festival, the contractor closed the westbound lanes, completing the same work on that side.

Because the NCDOT contractor finished prior to May 23, they will earn an additional $500,000.
For additional information about the preservation project, visit ncdot.gov/CFMBrehab.

Wilmington Traffic Patterns to Return to Original Movements

The evening of May 8, the barricades on 3rd Street will be removed and traffic will be restored at its normal pattern at U.S. 421 onto U.S. 74.

NCDOT staff will restripe 3rd Street beginning at 7 p.m. May 9.

The traffic pattern at U.S. 117 North (North College Road) onto U.S. 74 (Martin Luther King Jr. Parkway) will return to its original pattern during the nights of May 15 and 16, weather permitting.

Platform Removal and Counterweights

While all lanes of the Cape Fear Memorial Bridge will be open to traffic daily, additional work will need to be done, including removal of the platform underneath the bridge.

To remove the platform, crews will need to close the outside lane in each direction. Beginning May 9, the lane closures will take place nightly between 7 p.m. and 6 a.m. until the platform is removed. After the platform removal is complete, the contractor will need to lift the bridge on several occasions to modify the counterweights that were added to the bridge as the deck and stringers were removed. The work will be done between 7 p.m. and 6 a.m. on dates that will be announced later.

Drivers are encouraged to use DriveNC.gov for the most up-to-date travel information and avoid the Cape Fear Memorial Bridge during these times. If unavoidable, drivers should be alert to the lane closures and crews working on the bridge.

For real-time travel information, visit DriveNC.gov or follow NCDOT on social media.

About Author

Leave a Reply